Planning for the unexpected: Managing risk in ageing assets
At some point, equipment in every operating plant will need to be repaired, replaced or upgraded. In some cases, the next steps will be clear. In ageing plants, however, upgrades can reveal conditions that were difficult or impossible to identify during routine operation.
The most significant surprises are often hidden in parts of the plant that have been inaccessible for years, or even decades. An upgrade may suddenly expose these areas, introducing uncertainty into what might initially appear to be a straightforward project.
The real risk is the one you can’t see
These risks do not necessarily indicate shortcomings in plant maintenance. In many cases, the underlying conditions are simply difficult to observe.
Corrosion can develop behind walls or beneath floors without obvious external signs. Years of hardened build-up can conceal structural steel, while calcification or corrosion can make meaningful visual inspection difficult.
In other cases, existing drawings may no longer accurately represent what was constructed. Decisions made on site decades earlier may not have been reflected in the records, leaving project teams designing a tie-in against drawings that do not fully represent the current plant.
The uncertainty can extend well beyond structural steel. It can affect pipework and utilities, access and lifting arrangements, and the physical constraints associated with installing new equipment within an operating plant.
When the lowest-cost option carries the highest risk
I recently worked with a mine owner whose flotation cells were approaching the end of their operating life. These cells are used to separate valuable minerals from ore.
The condition of the supporting structure could not be confidently established because years of hardened build-up had encased much of the steelwork and severely restricted access for inspection. The structural risk was evident, but the full condition of the area would not become clear until the existing equipment was removed.
Rather than deferring that uncertainty to a later stage, we worked with the owner to assess three options.
The first was to replace the flotation cells in situ. On paper, this option had the lowest upfront cost, but it also carried the greatest shutdown and remediation risk. An estimated six-week shutdown could be extended if removal of the cells exposed unexpected structural, electrical or other problems.
The second option was to use available floor space elsewhere within the existing building. This reduced much of the hidden structural risk but retained another longstanding constraint: low overhead clearances. Existing maintenance activities required equipment to be lifted, manually slung sideways and moved out of position rather than lifted vertically using adequate crane access.
The third option was to construct the new flotation circuit in a separate structure outside the existing building. This required greater upfront capital, but reduced exposure to shutdown and hidden-condition risks while also addressing the existing maintainability constraint.
Looking only at initial capital cost could have favoured one of the first two options. Once potential production losses, execution risk and maintainability were considered, the owner could make a more informed investment decision.
A familiar challenge
Similar conditions can arise across ageing brownfield operations.
Sometimes the immediate driver is a structural problem and the balance between reliability, risk and return has shifted heavily towards risk. In other cases, an owner may be seeking to improve reliability through sustaining capital investment or increase returns through higher throughput or improved recoveries.
Whatever the reason for an upgrade, the principle is the same: project teams need to plan for conditions they cannot fully verify before work begins.
Five considerations can help manage this uncertainty:
Put the right experience in the room early. Brownfield decisions are rarely purely structural, mechanical or electrical. They involve constructability, shutdown duration, operations, maintainability and life cycle value. It is therefore important to involve people with practical brownfield execution experience, including construction, commissioning and operations expertise, alongside designers. This experience can help identify where problems are most likely to emerge, whether the project team designed the original plant or is encountering it for the first time.
Quantify the downtime before you quantify the cost. Initial capital cost is only one part of the comparison between options. The duration and production consequences of a shutdown can materially affect the overall business case. Potential production losses should therefore form part of the trade-off analysis alongside equipment and construction costs.
Price the unknown in, don’t assume it away. Inspect everything that can reasonably be inspected, then make appropriate allowances for conditions that cannot be verified. Targeted structural inspections can reduce uncertainty, while techniques such as laser scanning can provide valuable information around brownfield tie-in points where historical drawings may not accurately reflect the plant as constructed. Not every unknown can be eliminated, but teams can identify where exposure remains and account for it in project schedules and cost estimates.
Follow every change to its full consequence. Brownfield changes rarely stop at the immediate tie-in point. For example, an electrical modification may have implications for an existing switchboard or broader electrical infrastructure, depending on the scope and applicable requirements. Additional load could also require changes to the switchroom, high-voltage distribution system or incoming power supply. The same principle applies to water, piping and other utilities: understand the potential upstream consequences before committing to the scope.
Weigh maintainability as part of the return. An upgrade that resolves an immediate failure while retaining future maintenance constraints may simply shift cost and risk into later operations. Consider whether existing maintenance practices are acceptable, manageable through appropriate controls, or creating avoidable safety risks, downtime and costs. Not every inconvenience requires redesign, but issues that materially affect safety, access, reliability or shutdown duration should be considered as part of the project value equation.
Plan for what you can’t see
It is impossible to remove every unknown from an ageing plant. What project teams can control is the quality of the decisions made before work begins.
Understanding the uncertainty, its potential consequences and the available alternatives allows capital decisions to consider more than the initial project cost.
In an ageing plant, the most expensive problem is often the one that was hidden when the project began.