Skip to main content
Conference Proceedings

15th Australasian Tunnelling Conference 2014

Conference Proceedings

15th Australasian Tunnelling Conference 2014

PDF Add to cart

Improving Excavation Efficiency at the St Helena Tunnel Using Best Practice Drill and Blast Techniques

This paper is focused on blasting activities undertaken as part of the Pacific Highway Upgrade - Tintenbar to Ewingsdale - project (T2E). This is a priority 1' Pacific Highway road construction project in New South Wales (NSW), to be completed by mid-2015 (weather permitting). T2E will provide approximately 17 km of dual carriageway road starting at the northern end of the Ballina bypass and extending to the Ewingsdale interchange, and will complete the existing dual carriageway road between Ballina and the NSW/Queensland border.Roads and Maritime Services (RMS) (formerly the Roads and Traffic Authority) is delivering the project on behalf of the NSW state and federal governments. In October 2011, RMS awarded a contract to Baulderstone Pty Ltd (now Lend Lease Engineering Pty Ltd - Lend Lease) to design and construct T2E. One of the key elements in this project is the St Helena Tunnel.In order to avoid the steep grades of St Helena Hill, eliminate a well-known accident black spot and maintain the aesthetics of the Byron hinterland escarpment, RMS and Lend Lease prepared designs to construct a 434 m long dual carriageway tunnel, 46 m below the ridge line of St Helena Hill. Lend Lease elected, where geotechnical conditions permitted, to use drill and blast methods to excavate the full tunnel profile, instead of traditional mechanical excavation techniques.Since all blasting locations (both inside and outside the tunnel) were in close proximity to nearby residents, the NSW Department of Planning and Infrastructure imposed strict air blast overpressure (airblast), ground vibration (vibration) limits and limited working hours. Both RMS and Lend Lease recognised that these restrictions meant that nearby residents may be exposed to blasting activities for longer than was necessary. As a result, after close consultation and agreement with the nearby residents, RMS applied successfully to the NSW Department of Planning to increase the airblast and vibration limits, as well as the working hours.Working under these new conditions, Lend Lease employed a range of best practice drill and blast technologies provided by both Orica Australia Pty Ltd and Atlas Copco Mining and Rock Excavation to improve the safety and efficiency of blasting activities and to minimise the potential negative impacts of the blasting works on affected residents. These technologies included: the use of a continuous environmental monitoring system to record the results of the blast events and provide quick and easy reporting to key stakeholders to address RMS specification requirements electronic detonators to enable accurate hole detonation timing for vibration compliance and to give project engineers the flexibility and precision to alter each design to suit the geological profile of each face the use of two software programs and advanced drill rigs to enable the efficient design of blasts, electronic transfer of designs to the drill rigs, as well as in-hole monitoring and recording of drilling performance the use of a specialised bulk emulsion system to deliver fully coupled bulk explosives into face blastholes to maximise fragmentation, and decoupled bulk explosives into perimeter blastholes, to reduce overbreak and deliver a cleaner profile._x000D_
By taking a progressive approach towards the environmental restrictions and the work hours imposed, as well as utilising best practice blasting techniques, RMS and Lend Lease were able to blast with confidence and achieve their production deadlines and reduce the total cost of the project.Most importantly, RMS and Lend Lease were able to meet their environmental obligations and work constructively with the nearby residents to ensure that the blasting was undertaken as safely and efficiently as possible without delay or negative impact.CITATION:Dowling, M, Domotor, R and Miller, D, 2014. Improving excavation efficiency at the St Helena Tunnel using best practice drill and blast techniques, in Proceedings 15th Australasian Tunnelling Conference 2014, pp 29-40 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Return to parent product
  • Improving Excavation Efficiency at the St Helena Tunnel Using Best Practice Drill and Blast Techniques
    PDF
    This product is exclusive to Digital library subscription
  • Improving Excavation Efficiency at the St Helena Tunnel Using Best Practice Drill and Blast Techniques
    PDF
    Normal price $22.00
    Member price from $0.00
    Add to cart

    Fees above are GST inclusive

PD Hours
Approved activity
  • Published: 2014
  • PDF Size: 2.793 Mb.
  • Unique ID: P201411004

Our site uses cookies

We use these to improve your browser experience. By continuing to use the website you agree to the use of cookies.