Development in Elevated Temperature Ground of the 500 Orebody Mount Isa Mines
The 500 orebody in the upper levels of Mt Isa Mines in north-west Queensland was mined by sublevel caving and block caving from 1962 to 1969. The hot and reactive rock mass of this orebody provided significant mining challenges including ground temperatures above those resulting from the geothermal gradient._x000D_
Recently Xstrata Copper has been studying the potential to mine this orebody by modern caving techniques. Part of the study process has included re-accessing the ore zones for diamond drilling and trial development._x000D_
A cross-cut trial drive, the first primary development into the orebody in more than 30 years, encountered a temperature increase in development holes from low sixties to almost 80C in less than 10 m advance. The issues associated with managing this risk include sourcing suitable quantities of reactive ground explosives for a single small heading and the temperature limitations of the explosives and detonators._x000D_
Risk management outcomes included controls to mitigate the safety and reliability risks relating to misfires. The control that dealt directly with the challenge of continuing development in elevated temperature ground was to cool the holes before and during charging. The most effective and practical cooling medium proved to be water. Rapid rock temperature recharge time meant cooling had to continue as close to firing as possible. Reticulation systems were constructed to allow cooling to take place up until withdrawal for firing. No misfires occurred with the cooling system and additional controls in place. This proved that developing safely and effectively in the elevated ground temperatures of the 500 orebody is practicable._x000D_
FORMAL CITATION:Faulkner, J and Davis, T, 2008. Development in elevated temperature ground of the 500 orebody Mount Isa mines, in Proceedings New Leaders' 2008, pp 27-32 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Recently Xstrata Copper has been studying the potential to mine this orebody by modern caving techniques. Part of the study process has included re-accessing the ore zones for diamond drilling and trial development._x000D_
A cross-cut trial drive, the first primary development into the orebody in more than 30 years, encountered a temperature increase in development holes from low sixties to almost 80C in less than 10 m advance. The issues associated with managing this risk include sourcing suitable quantities of reactive ground explosives for a single small heading and the temperature limitations of the explosives and detonators._x000D_
Risk management outcomes included controls to mitigate the safety and reliability risks relating to misfires. The control that dealt directly with the challenge of continuing development in elevated temperature ground was to cool the holes before and during charging. The most effective and practical cooling medium proved to be water. Rapid rock temperature recharge time meant cooling had to continue as close to firing as possible. Reticulation systems were constructed to allow cooling to take place up until withdrawal for firing. No misfires occurred with the cooling system and additional controls in place. This proved that developing safely and effectively in the elevated ground temperatures of the 500 orebody is practicable._x000D_
FORMAL CITATION:Faulkner, J and Davis, T, 2008. Development in elevated temperature ground of the 500 orebody Mount Isa mines, in Proceedings New Leaders' 2008, pp 27-32 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Contributor(s):
J Faulkner, T Davis
-
Development in Elevated Temperature Ground of the 500 Orebody Mount Isa MinesPDFThis product is exclusive to Digital library subscription
-
Development in Elevated Temperature Ground of the 500 Orebody Mount Isa MinesPDFNormal price $22.00Member price from $0.00
Fees above are GST inclusive
PD Hours
Approved activity
- Published: 2008
- PDF Size: 1.652 Mb.
- Unique ID: P200806007